City work continues to replace old water, sewer infrastructure
MEDICINE HAT, AB — The final stage of replacing aging water and sewer infrastructure along Division Avenue South begins on July 23.
The intersection at 10th Street and Division Avenue will be closed until about Aug. 6, barring adverse weather and unforeseen delays. Detours will be in place throughout the work period.
In this final stage, crews will remove and replace an air release valve and water vault.
The city says that once this phase is complete, work for this project — which restores underground infrastructure and improves isolation boundaries in the water distribution system — within the roadway of Division Avenue will be complete.